Question no 4212 : Engineering Change scenario

 In SAP S/4 1909, identify the possible Engineering Change Master scenario based on the following ECM Change Master applied to the the Material BOM ?


(only one answer)

A)  Leading Change Master with the Valid dates in the Change Packages.
B)  Change Packages with the Valid dates in the Leading Change Master.
C)  Change Master without approved Validity dates.
D)  Change Master with and appropriate Effectivity Type.
E)  The Change Master with a Release Key has not been approved Globally.
.

Answer: D

When using Change Master with Effectivity Type, it is not necessary to have dates as the BOM Explosion for ECM selection will be based on the Effectivity Values entered instead of by Date.