In SAP MM and PP, which of the following is correct about MRP Area ?

(more then one answers)

A)    MRP Area is optional and material specific.
B)    One MRP Area can be assigned with more then one Storage Location.
C)    MRP planning run can be executed at the MRP Area level.
D)    An MRP Area can have either one or more Storage Locations.
E)    The Stocks Requirements List can be viewed at the MRP Area level.
.