This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, July 8, 2011

Question no 1098 : Goods Receipt Processing time

In SAP MM and PP, the GR Processing time is ______________________ .

(only one answer)

A)    used to derive the Stock Available Date.
B)    used to derive the Goods Receipt Date.
C)    used to derive the PO Finish/End Date.
D)    used to derive the PO Completion Date.
E)    used to derive the PO Opening Date.
.