Question no 3643 : Sampling Procedure

In SAP QM as at ECC6.0 EhP6, which of the following Sampling Procedure assignment is correct ?

(more than one answers)

A)  Material Master QM data view for each Inspection Type.
B)  Master Inspection Characteristic.
C)  Inspection Plan Header.
D)  Inspection Plan Operation's Master Inspection Characteristics assignment screen.
E)  Material Specification Master Inspection Characteristics assignment screen.
.

Answers: A, D, E

Only those 3 mentioned in the answer

Monday, May 20, 2019

Question no 3642 : Quota Arrangement Usage

In SAP MM as at ECC6.0 EhP6, which of the following is required to be able to activate the use of the Quota Arrangement ?

(only one answer)

A)  Quota Arrangement Usage in the Material Master.
B)  Quota Arrangement Usage in the Plant Parameter.
C)  Quota Arrangement Usage in the Vendor Master.
D)  Quota Arrangement Usage in the Purchasing Info Record.
E)  Quota Arrangement Usage in the Purchasing Organization.
.

Answer: A

You can find the Quota Arrangement Usage in the MRP data view.

Wednesday, May 15, 2019

Question no 3641 : Plant Maintenance General Task List

In SAP PM as at ECC6.0 EhP6, which of the following is TRUE about the General Task List ?

(only one answer)

A)  General Task List's Group number can be internal or external number.
B)  General Task List's Counter can only be numeric.
C)  General Task List's Header can be assigned to a one or more Plants.
D)  General Task List can be created without Plant which is called a Group General Task List.
E)  General Task List can be assigned to one or more Equipment Masters.
.

Answer: A

B) Counter can be both alphanumeric or numeric with 2 characters.
C,D) G.Task List must be assigned to one Planning Plant.
E) G.Task List cannot be assigned to FL or EQ.
 

Tuesday, May 7, 2019

Question no 3640 : Planning in PP

In SAP PPDI or PPPI as at ECC6.0 EhP6, which of the following is not a Planning Module in PP ?

(only one answer)

A)  SOP.
B)  LTP.
C)  MPS.
D)  MRP.
E)  SFC.

Answer: E

SFC = Shop Floor Control is an Execution Module.