In SAP PM as at ECC6.0 EhP6, which of the following is TRUE about the General Task List ?
(only one answer)
A) General Task List's Group number can be internal or external number.
B) General Task List's Counter can only be numeric.
C) General Task List's Header can be assigned to a one or more Plants.
D) General Task List can be created without Plant which is called a Group General Task List.
E) General Task List can be assigned to one or more Equipment Masters.
.
Answer: A
B) Counter can be both alphanumeric or numeric with 2 characters.
C,D) G.Task List must be assigned to one Planning Plant.
E) G.Task List cannot be assigned to FL or EQ.
(only one answer)
A) General Task List's Group number can be internal or external number.
B) General Task List's Counter can only be numeric.
C) General Task List's Header can be assigned to a one or more Plants.
D) General Task List can be created without Plant which is called a Group General Task List.
E) General Task List can be assigned to one or more Equipment Masters.
.
Answer: A
B) Counter can be both alphanumeric or numeric with 2 characters.
C,D) G.Task List must be assigned to one Planning Plant.
E) G.Task List cannot be assigned to FL or EQ.