Question no 4233: Material with Material Type "UNBW" and "NLAG" in the Material BOM

In SAP Production Planning, the following 2 Materials:
Material UNBW01 created with Material Type UNBW
Material NLAG01 created with Material Type NLAG
Which of the following are TRUE about including the 2 Materials in a Material BOM ?
 

(more than one answers) 

A)  Material UNBW01 can be created with Item Category "L" in the Material BOM.
B)  Material NLAG01 can be created with Item Category "L" in the Material BOM. 
C)  Material UNBW01 can be created with Item Category "N" in the Material BOM.
D)  Material NLAG can be created with Item Category "N" in the Material BOM.
E)  All of the above. 
.

Answer: A, C, D