Q&A in Class (2026-07-24) S4520

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Question: ME91FF Dunning Report do not process Reminder properly in a class exercise simulation.
eg: Today's date or Reference date is 25 July 2026
PO #123 Item10 Material T-R122 with Delivery date 26.July.2026
PO #123 Item20 Material T-R222 with Delivery date 25.August.2026
Reminder 1: -2 days
Reminder 2: +2 day
Reminder 3: +5 days
why ME91FF with Reference date 25 July 2026 shows PO#123 Item 10 & Item 20 in the Dunning (Reminder) Report which is correct for Item 10's Delivery date of 26.July.2026 but NOT CORRECT for Item 20's Delivery date of 25 August 2026. 


Answer: No configuration were changed, the PO created manually with assignment of Reminder days manually in the PO item (similar if default from Purchasing Value Key Reminder days). The following is the simulation results with below link.

Click here to view the Simulation Results:

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------