In SAP QM ECC6.0 EhP6, study the graphics and determine why it is possible to perform UD for the Inspection Lot despite Sample Size is ZERO ?
(only one answer)
A) Physical Sample Drawing Procedure was activated.
B) Auto UD was done.
C) It was a 'SKIP' lot.
D) User Authorization to by-pass RR.
E) Inspection setup without Inspection Specifications Requirements.
.
(only one answer)
A) Physical Sample Drawing Procedure was activated.
B) Auto UD was done.
C) It was a 'SKIP' lot.
D) User Authorization to by-pass RR.
E) Inspection setup without Inspection Specifications Requirements.
.
Answer: E
ReplyDeleteRefer the Setup in Graphics on Question no 2749.
ReplyDelete