Question no 2558 : Requirements for MRP run

In SAP MRP, which of the following is mandatory for MRP execution ?

(only one answer)

A)   Purchasing Info Record.
B)   Soure List.
C)   Quota Arrangement.
D)   MRP Group Parameter.
E)   Plant Parameter.
.

1 comment:

  1. Based on the list, OPPQ or Plant Parameter is the only setting mandatory. Quota Arrangement, Source List, and PIR are only required if source determination is desirable during MRP run but not mandatory. MRP Group Parameter is secondary to the Plant Parameter, it is only needed if fine tuning of MRP Parameters for groups if material is desirable but not mandatory.