This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Tuesday, July 12, 2011

Question no 1149 : Quota Arrangement calculation

In SAP MM and PP, assume the following data and determine the source determination during an MRP Run for the requirement quantity of 1200 ?

Material master is assigned with Lot Sizing "ES".
(Assuming Quota-Based Qty : 0 for all Vendors in the Quota Arrangement)

Quota for Vendor A : 1, Allocated Qty : 1200 
Quota for Vendor B : 2, Allocated Qty : 1400  
Quota for Vendor C : 3, Allocated Qty: 4800, max quantity 2000
Minimum to Split is 1000

Deduce the correct statement from below. 
(only one answer) 

A)     One Supply to Vendor B with the 1200 quantity. 
B)     4 supplies created, Vendor A gets 200, Vendor B gets 400, Vendor C gets 400, and a PR without vendor of 200. 
C)     3 supplies created, Vendor A gets 300, Vendor B gets 500, Vendor C gets 400.
D)     3 supplies created, Vendor A gets 200, Vendor B gets 400, Vendor C gets 600.
E)     Vendor A gets 400, Vendor B gets 800 in two different supplies.
.