In SAP MM, what is the best method to ensure the source list is required for a particular material master of a plant ?

(only one answer)

A)    set the source list requirement at the Plant level in the configuration.
B)     set the source list requirement at the Purchasing Organization level in the configuration.
C)     set the source list requirement at the MRP1 view of the Material Master.
D)     set the source list requirement at the Purchasing view of the Material Master.
E)     set the source list requirement at the Purchasing Info Record.
.