In SAP MM and PP, select the correct statement comparing MRP List and S/R List.
(more then one answers)
A) the MRP List is dynamic while the S/R List is static.
B) the MRP List is static while the S/R List is dynamic.
C) the MRP List can be generated from the MRP Planning run.
D) the S/R List do not have a memo entry facility while the MRP List has.
E) the S/R List allows the user to convert a Planned Order to a Purchase Requisition while the MRP List cannot do so.
.
(more then one answers)
A) the MRP List is dynamic while the S/R List is static.
B) the MRP List is static while the S/R List is dynamic.
C) the MRP List can be generated from the MRP Planning run.
D) the S/R List do not have a memo entry facility while the MRP List has.
E) the S/R List allows the user to convert a Planned Order to a Purchase Requisition while the MRP List cannot do so.
.
Answer: B, C