Question no 1096 : Lot Size calculation

In SAP MM PP, Please use the following information to derive the expected MRP calculation results of the Lot Size ?

Current Stocks = 50
No other MRP element exist except the following
      one Purchase Order of 250 within the Replenishment Period.
      one Reservation of 50 with the Replenishment Period.
Safety Stock is 0
MRP type is Re-Order Point "VB" with ROP at 500
Lot Sizing key is "EX", minimum Lot Size is 70, maximum Lot Size is 200
Rounding Profile of the following
     1 - 99 round to 20
     100 - 599 round to 100
     599 - 9999 round to 500

(only one answer)

A)    A Planned Orders 200 and Two Planner Orders of 40 each.
B)    Two Planned Orders 100 each and Two Planner Orders of 40 each.
C)    14 Planned Orders of 20 each.
D)    A Planned Order 200 and Another Planner Order of 80.
E)    A Planned Order of 280.
.