Question no 1090 : Lot Size calculation

In SAP MM & PP, Please use the following information to derive the expected MRP calculation results of the Lot Size ?

Current Stocks = 250
No other MRP element exist except one Purchase Order of 100 within the Replenishment Period.
Safety Stock is 0
MRP type is Re-Order Point "VB" with ROP at 800
Lot Sizing key is "EX" and minimum lot size is 500 
Rounding Value = 12

(only one answer)

A)    A Planned Order of 504. 
B)    A Planned Order of 500.
C)    A Planned Order of 500 and Another Planner Order of 4.
D)    42 Planned Orders of 12 each.
E)    A Planned Order of 456.
.