Question no : 337 MM Organization Purchasing-Specific scenario

TERP10 (Unit 3) Procurement Cycle 

In a Plant-Specific Purchasing Organization scenario, the purchasing organization is responsible for .....

(Select ONE best answer)

A)   procuring for a purchasing group that is assigned to the material master. 
B)   procuring for one or more plants that belong to the same company. 
C)   procuring for more then one plant that belong to more then one company. 
D)   procuring for plants that belong to one company. 
E)    procuring materials for only one plant. 