In SAP MM or PP as at ECC6.0 EhP6, which of the following field in the Lot Size key configuration allows you to set MRP run to generate staggered delivery for a Requirement using Forward or Backward rules ?
(only one answer) 
A)   Lot size indicator and No. of periods
B)   Scheduling method
C)   Date Interpretation
D)   Overlapping
E)   Splitting quota
.

Refer to http://cwwongsap.blogspot.my/search/label/~%20MRP%20Lot-Size%20with%20Backward%20Overlap