This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes
▼
Thursday, August 31, 2023
Thursday, August 24, 2023
Question no 3975 : Production Planning LTP characteristics
In SAP Production Planning, pick up the correct statements about SAP LTP (Long Term Planning) ?
(more than one answers)
A. LTP Scenario can be setup to explode a specific BOM usage.
B. LTP planned orders can be converted to Purchase Requisitions and copied to the Operative Planned Orders.
C. SOP planning versions can be assigned to LTP Scenarios.
D. Consumption based Planning materials can be included in LTP scenario for dependent requirement calculation.
E. LTP Scenario can be setup to select Routing based on Usage and Status.
.
Answer: A, D, E
A) A selection ID that prioritize BOM usage selection can be assigned to the LTP Scenario.
B) LTP Planned Orders cannot be converted to Purchase Requisitions.
C) Only Planned Independent Requirement Versions can be included in the LTP Scenario and not the SOP Versions.
D) MM Consumption based Planning included in the LTP Scenario can be treated with Independent-Dependent Requirement calculations to determine its possible requirement in the LTP Planning run to facilitate Supplier negotiation and Inventory Planning.
E) There are no facilities in the LTP Scenario to select a specific Routing or Recipe; however, a Capacity Version from the Work Center can be assigned.