This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes
▼
Wednesday, September 28, 2022
Sunday, September 25, 2022
Question no 3947 : Set up Cost Collector for Production Order
In SAP ECC6 EhP8, which of the following is used to activate Cost Collect or Period based Costing for Production Order ?
(only one answer)
A) Plant Parameters.
B) Production Scheduler.
C) Production Scheduler Profile.
D) Order Type Plant dependent Parameter.
E) Material Master Work Scheduling view.
.
Answer: D
(only one answer)
A) Plant Parameters.
B) Production Scheduler.
C) Production Scheduler Profile.
D) Order Type Plant dependent Parameter.
E) Material Master Work Scheduling view.
.
Answer: D
Wednesday, September 21, 2022
Saturday, September 17, 2022
Question no 3946 : Invoice Automatically Release
In SAP ECC6 EhP8 for Materials Management in Invoice Verification, which of the following cases where a Blocked Invoice be Released Automatically via MRBR (with a condition Purchase Order cannot be changed after Approval for Vendor Transmission) ?
(more than one answers)
A) Invoice Block due to Quantity.
B) Invoice Block due to Price.
C) Invoice Block due to Quality.
D) Invoice Block due to Date.
E) Invoice Block due to Stochastic Block.
Answer: A, C, D
A) An Invoice can be blocked due to Quantity variance, especially Invoice before GR and subsequent Goods Receipt after the Invoice entry.
B) An Invoice blocked due to Price variance cannot be released automatically (unless the PO price is changed to match the variance differences); however, in most cases after the PO is approved, often Release Strategy field selection will no longer allow price to be changed. In addition, company policy should have dictated no changes to prices of PO after the PO is approved.
C) An Invoice is entered before Inspection Lot Usage Decision but will be block for payment. After the Inspection Lot UD accepted, the blocked Invoice can now be Released automatically. But if the UD rejected then the block Invoice can only be Released manually.
D) Invoice Block due to Date can occur when Invoice is entered before the Delivery date; however, when the current date is now beyond the delivery date then the Blocked Invoice should not be blocked and therefore can be Released automatically.
E) Stochastic block will block the Invoice at the Header level and can only be Released manually.
(more than one answers)
A) Invoice Block due to Quantity.
B) Invoice Block due to Price.
C) Invoice Block due to Quality.
D) Invoice Block due to Date.
E) Invoice Block due to Stochastic Block.
Answer: A, C, D
A) An Invoice can be blocked due to Quantity variance, especially Invoice before GR and subsequent Goods Receipt after the Invoice entry.
B) An Invoice blocked due to Price variance cannot be released automatically (unless the PO price is changed to match the variance differences); however, in most cases after the PO is approved, often Release Strategy field selection will no longer allow price to be changed. In addition, company policy should have dictated no changes to prices of PO after the PO is approved.
C) An Invoice is entered before Inspection Lot Usage Decision but will be block for payment. After the Inspection Lot UD accepted, the blocked Invoice can now be Released automatically. But if the UD rejected then the block Invoice can only be Released manually.
D) Invoice Block due to Date can occur when Invoice is entered before the Delivery date; however, when the current date is now beyond the delivery date then the Blocked Invoice should not be blocked and therefore can be Released automatically.
E) Stochastic block will block the Invoice at the Header level and can only be Released manually.
Wednesday, September 14, 2022
Saturday, September 10, 2022
Wednesday, September 7, 2022
Saturday, September 3, 2022
Question no 3945 : Plant Maintenance System Status
In SAP Plant Maintenance as at ECC6 EhP8, which of the following System Status for Maintenance Order can be Reversed ?
(more than one answers)
A) "REL" Released status.
B) "TECO" Technically Completed status.
C) "CLSD" Business Closing status.
D) "CLSD" Do not Execute status.
E) "LKD" Locked status.
Answer: B, C, D, E
A) "REL Release status cannot be reverse for Maintenance Order or Service Order.
D) Only when the Maintenance Order is at "CRTD" status that it can be set with "CLSD" (Do not Execute) BUT that status can be reverted back to "CRTD".
(more than one answers)
A) "REL" Released status.
B) "TECO" Technically Completed status.
C) "CLSD" Business Closing status.
D) "CLSD" Do not Execute status.
E) "LKD" Locked status.
Answer: B, C, D, E
A) "REL Release status cannot be reverse for Maintenance Order or Service Order.
D) Only when the Maintenance Order is at "CRTD" status that it can be set with "CLSD" (Do not Execute) BUT that status can be reverted back to "CRTD".
E) The "LKD" (Locked) status can be implemented on the Maintenance Order at "CRTD" (Created) or "REL" (Release Status) and can be reverted in both cases.
Conclusion:
- "REL" (Release) status cannot be reverted to "CRTD" status.
- "TECO" (Technical Completion) status can be reverted.
- "CLSD" (Business Closing) via Black and White FLAG can be reverted.
- "CLSD" (Do not Execute) is possible to be set using Order - Function - Complete - Do not Execute, and is possible only when Order is at "CRTD" (Created) status and this can be reverted from "CLSD" to "CRTD".
- "LKD" (Locked) status can be implemented either when Order is at "CRTD" (Created) or "REL" (Release Status) or "TECO" or "CLDS" and can be reverted in all cases.
- "DEL" (Deletion Flag) status can be implemented when Order is at "CLSD" (Closed) status and this also can be reverted.