This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Monday, July 25, 2022

Question no 3941 : Operation Scrap Factor and Assembly Scrap Factor

In SAP ECC 6.0 Ehp7, use the following data to calculate the Cost of the Raw Material.

F100 Assembly Scrap Factor 20%
M100 Component Scrap Factor (BOM) 5% 
M100 Component Scrap Factor (Material) 10%
M100 Operation Scrap Factor 10%
M100 Price $20/pc
BOM shows to produce 1 pc of F100 requires 1 pc of M100

What is the Cost of the Raw Material ?

(only one answer)

A) $12.60
B) $22.00
C) $23.10
D) $13.60
E) $22.06

Answer: C

Explanations:
M100
with Operation Scrap Factor (Assembly Scrap factor will be ignore)
M100 Component Scrap Factor (BOM) 5% is Priority 1 will be used)
1+(1 x 10%) (Opr Scrap Factor) = = 1.10
1.10 + (1.10 x 5%) (Compo.Scrap from BOM) = = 1.155
M100 Cost 1.155 x $20 = $23.10

Wednesday, July 13, 2022

Question no 3940 : Assembly Scrap Factor and Component Scrap Factor (2)

In SAP ECC 6.0 Ehp7, use the following data to calculate the Cost of the Raw Material.

Finished Goods with Assembly Scrap Factor 5%
Raw Material with Component Scrap Factor in the Material Master 10%
Raw Material with Component Scrap Factor in the Material Master 5%
BOM show 1 pc of Raw Material to product 1 pc of Finished Goods
Raw Material MAP is $20/pc

What is the Cost of the Raw Material ?

(only one answer)

A) $12.60
B) $22.00
C) $23.10
D) $13.60
E) $22.06

Answer: E

Explanations:
Assembly Scrap Factor 5%
Component Scrap Factor 10%
1+ (1 x 5%) = 1.05
1.05 + (1.05 x 5%) = 1.1025
Raw Material Costs is 1.1025 x $20 = $22.05
In SAP, there my be rounding to 3 decimals
so
1.05 + (1.05 x 5%) = 1.1025 >> 1.103
Raw Material Costs could be 1.103 x $20 = $22.06

Monday, July 11, 2022

Question no 3939 : Assembly Scrap Factor and Component Scrap Factor (1)

In SAP ECC 6.0 Ehp7, use the following data to calculate the Cost of the Raw Material.

Finished Goods with Assembly Scrap Factor 20%
Raw Material with Component Scrap Factor 5%
BOM show 1 pc of Raw Material to product 1 pc of Finished Goods
Raw Material MAP is $10/pc

What is the Cost of the Raw Material ?

(only one answer)

A) $12.60
B) $12.00
C) $10.00
D) $13.60
E) $18.00

Answer: A

Explanations:
Assembly Scrap Factor 20%
Component Scrap Factor 5%
1+ (1 x 20%) = 1.20
1.20 + (1.20 x 5%) = 1.26
Raw Material Costs is 1.26 x $10 = $12.60

Saturday, July 2, 2022

Question no 3938 : APO Product view

In SAP S/4 1809, which of the following features are possible in the Product view (SAPAPO/RRP3) ?

(more than one answers)

A) Create Planned Order manually.
B) Heuristic run to Generate Planned Orders.
C) Create Purchase Orders.
D) Set Conversion Indicator for Planned Orders to Prod Orders.
E) Set Conversion Indicator for PR to PO.
.

Answers: A, B, D

. A variety of Heuristics can be executed interactively in the Product view.
. There is a facility to manually create Planned Orders (for Inhouse Production Materials)
. There is a facility to manually create MRP PRs (for External Procurement Materials)
. For Inhouse Production Materials, there is a Conversion indicator but actual conversion is done externally (not in Advanced Planning)