Question no 3703 : Activating QM Costing

In SAP QM as at ECC6.0 EhP6, which of the following is to activate QM for costing for an Inspection Lot ?

(only one answer)

A)  Settings in the Inspection Type in the Material Master QM data view.
B)  Settings in the Inspection Lot Document Type.
C)  Settings in the Master Inspection Characteristics.
D)  Settings in the Sampling Procedure.
E)  Settings in the Sampling Scheme.
.

Answer: A

A) You can either assign a QM Order or setting to have one QM Order per Inspection Lot in the Inspection Type assigned in the QM data view in the Material Master.

Question no 3702 : Contract

In SAP MM as at ECC6.0 EhP6, which of the following is CORRECT about the Purchasing Contract ?

(more than one answers)

A)  Goods Receipt is possible with reference to a Contract.
B)  A Scheduling Agreement can be created with reference to a Contract.
C)  A Purchase Order can be created with reference to a Contract.
D)  A Contract item can generate into a Source List.
E)  A Contract can be saved without a Plant.
.

click (1 comment) for suggested answer

Thursday, June 25, 2020

Question no 3701 : Material Master without Accounting Data view

In SAP MM as at ECC6.0 EhP6, which of the following is the response of SAP when entering a Material Master without an Accounting Data View in a Purchasing Order ?

(only one answer)

A)  Abap Dump.
B)  Request for Estimated Price.
C)  No Response.
D)  System disallow and Exits.
E)  Request for Account Assignment.
.

click (1 comment) for suggest answer

Question no 3700 : Source Determination

In SAP MM as at ECC6.0 EhP6, which of the following provides the Source but not the Price in a Source Determination process ?

(more than one answers)

A)  Quota Arrangement.
B)  Source List.
C)  Contract.
D)  Scheduling Agreement.
E)  Purchasing Info Record.
.

Tuesday, June 16, 2020

Question no 3699 : Time Based Floats

In SAP PP as at ECC6.0 EhP7, which of the following are examples of Time Based Floats in an MRP run and Production Order creation ?

(more than one answers)

A)  Safety Time.
B)  Safety Stock.
C)  Dynamic Safety Stock.
D)  Float Before Production.
E)  Float After Production.
.

click (1 comment) for suggested answers

Wednesday, June 10, 2020

Question no 3698 : Production Version

In SAP PP as at ECC6.0 EhP6, which of the following can be defined in a Production Version ?

(more than one answers)

A)  Goods Issue Storage Location.
B)  Goods Receipt Storage Location.
C)  Lot Size.
D)  BOM, Routing, or Recipe.
E)  Backflushing indicator.
.

click "1 comment" for suggested answers

Wednesday, June 3, 2020

Question no 3697 : MRP Mechanics with BOM Explosion

IN SAP PP as at ECC6.0 EhP6, which of the following settings must present for the BOM Explosion step of the MRP run to take place ?

(more than one answers)

A)  An appropriate MRP Type.
B)  A BOM.
C)  A Routing.
D)  A Production Version.
E)  A Planning Horizon.
.

click "1 comment" for suggested answers.