Question no 3687 : QM data creation
In SAP QM as at ECC6.0 EhP7, which of the following in QM cannot be created by the User as it is provided/delivered by SAP ?
(only one answer)
A) Inspection Origin.
B) Inspection Type.
C) Sampling Procedure.
D) Sampling Scheme.
E) Dynamic Modification.
.
Answer: A
Inspection Origin is delivered by SAP as standard.
(only one answer)
A) Inspection Origin.
B) Inspection Type.
C) Sampling Procedure.
D) Sampling Scheme.
E) Dynamic Modification.
.
Answer: A
Inspection Origin is delivered by SAP as standard.
Monday, March 23, 2020
Thursday, March 19, 2020
Wednesday, March 18, 2020
Question no 3686 : ERS
In SAP MM as at ECC6.0 EhP6, which of the following require the ERS setting in order to generate the Invoice Automatically ?
(more than one answers)
A) Invoicing Plan.
B) Pipeline Settlement.
C) Consignment Settlement.
D) Blanket Purchase Order Settlement.
E) Background Invoice Posting.
.
Answers: A, B, C
D) Blanket PO do not have GR, only manual Invoice can post the Invoice.
E) Background Invoice Posting is expected to be entered manually and not auto generated.
(more than one answers)
A) Invoicing Plan.
B) Pipeline Settlement.
C) Consignment Settlement.
D) Blanket Purchase Order Settlement.
E) Background Invoice Posting.
.
Answers: A, B, C
D) Blanket PO do not have GR, only manual Invoice can post the Invoice.
E) Background Invoice Posting is expected to be entered manually and not auto generated.
Monday, March 16, 2020
Sunday, March 15, 2020
Saturday, March 14, 2020
Thursday, March 12, 2020
Wednesday, March 11, 2020
Question no 3685 : Maintenance Order Closing
In SAP PM as at ECC6.0 EhP7, which of the following is used to determine which cost element is used to credit the cost from the Maintenance Order to the Settlement Receiver ?
(only one answer)
A) Valuation Variant.
B) Costing Variant.
C) Allocation Structure.
D) Costing Sheet.
E) Settlement Rule.
.
Answer: C
The Allocation Structure assigned tot he Settlement Profile is used to achieve this.
(only one answer)
A) Valuation Variant.
B) Costing Variant.
C) Allocation Structure.
D) Costing Sheet.
E) Settlement Rule.
.
Answer: C
The Allocation Structure assigned tot he Settlement Profile is used to achieve this.
Monday, March 9, 2020
Saturday, March 7, 2020
Thursday, March 5, 2020
Wednesday, March 4, 2020
Question no 3684 : Purchasing Info Record update
In SAP MM as at ECC6.0 EhP6, which of the following Purchasing Documents only updates the Purchasing Info Record as the Last Purchasing Document ?
(only one answer)
A) Purchase Requisition.
B) RFQ.
C) Purchase Order.
D) Contract.
E) Scheduling Agreement.
.
Answer: C
PO only create or Update the PIR as the last PO number.
(only one answer)
A) Purchase Requisition.
B) RFQ.
C) Purchase Order.
D) Contract.
E) Scheduling Agreement.
.
Answer: C
PO only create or Update the PIR as the last PO number.
Tuesday, March 3, 2020
Question no 3684 : PRT in Routing
In SAP PP as at ECC6.0 EhP6, which of the following PRT type can be assigned to the Routing Operations ?
(more than one answers)
A) Document PRT.
B) Miscellaneous PRT.
C) Equipment PRT.
D) Material PRT.
E) Measuring Point.
.
Answers: A, B, C, D
Except Measuring Point.
(more than one answers)
A) Document PRT.
B) Miscellaneous PRT.
C) Equipment PRT.
D) Material PRT.
E) Measuring Point.
.
Answers: A, B, C, D
Except Measuring Point.