Question no 3675 : Repetitive Manufacturing

In SAP PP as at ECC6.0 EhP6, which of the following are correct about Repetitive Manufacturing ?

(more than one answers)

A)  REM Planned Orders can be generated via MRP Run.
B)  Goods Issue and Goods Receipt is possible with reference to a REM Planned Orders.
C)  REM Planned Orders can collect costs just like a Production Orders.
D) BOM and Routing are optional in Repetitive Production Version.
E)  REM Planned Orders can be viewed in the Stocks Requirements Lists.
.
Click "1 comment" for Suggested answers

Wednesday, December 18, 2019

Question no 3674 : Goods Movement without Valuation

In SAP MM as at ECC6.0 EhP7, which of the following Goods Movement Scenarios do not result in Valuation (Accounting Postings) ?

(more than one answers)

A)  Goods Receipt with reference to Consignment Purchase Order.
B)  Goods Receipt with reference to Subcontracting Purchase Order.
C)  Goods Receipt with reference to Pipeline Purchase Order.
D)  Goods Receipt with reference to Consumable Purchase Order.
E)  Goods Receipt with reference to "UNBW" Material Type Purchase Order.
.

Click "1 comment" to check Possible answers

Wednesday, December 11, 2019

Question no 3673 : Planning Plant

In SAP PM as at ECC6.0 EhP7, which of the following is where Planning Plant applicable ?

(more than one answers)

A)  General Task List Header as a mandatory field.
B)  Maintenance Plan Header as a mandatory field.
C)  Maintenance Order initial screen as a mandatory field.
D)  Maintenance Notification initial screen as a mandatory field.
E)  Work Center initial screen as a mandatory field.
.

Answers: A, C

B, D) Both Maintenance Plan and Maintenance Notification Header do not necessarilly require a Plant defination in its Header of Maintenance Item for certain Maintenance Plan acenario.
E) Work Center is created with maintenance Plant.
.

Wednesday, December 4, 2019

Question no 3672 : MRP can generate

In SAP PP as at ECC6.0 EhP7, which of the following can MRP Generate ?

(more than one answers)

A)  Purchase Requisition.
B)  Purchase Order.
C)  Delivery Schedule for Scheduling Agreement.
D)  Planned Order.
E)  RFQ.
.
click "1 comment" to display possible Solution

Wednesday, November 27, 2019

Question no 3671 : Plant

In SAP MM as at ECC6.0 EhP6, which of the following scenario can be created without a Plant ?

(more than one answers)

A)  Create a Purchasing Info Record.
B)  Create an RFQ.
C)  Create a Contract.
D)  Create a Scheduling Agreement.
E)  Create a Source List.
.

Click on the "1 comment" to check possible Answers

Tuesday, November 19, 2019

Question no 3670 : Planned Independent Requirement Creation

In SAP PP as at ECC6.0 EhP6, what are the possible methods of creating Planned Independent Requirements ?

(more than one answers)

A)  Copy from Sales Information System.
B)  Copy from Sales and Operations Plan.
C)  Copy from COPA.
D)  Executing a Forecast.
E)  Copy from Stocks Requirements List.
.

Wednesday, November 13, 2019

Question no 3669 : Object List in Maintenance Order

In SAP PM as at ECC6.0 EhP6, which of the following are possible Objects that can be assigned in the Object Lists in the Maintenance Order ?

(more than one answers)

A)  Serial number.
B)  Equipment.
C)  Functional Location.
D)  Maintenance Notification.
E)  Measuring Point.
.

Answer: E

Except MP

Wednesday, November 6, 2019

Question no 3668 : Purchase Requisition

In SAP MM as at ECC6.0 EhP6, which of the following possible for Purchase Requisition ?

(more than one answers)

A)  Copy to another Purchase Requisition.
B)  Convert to a RFQ.
C)  Convert to a Contract.
D)  Convert to a Scheduling Agreement.
E)  Convert to a Purchase Order.
.

Answers: A, B, C, D, E

All possible.

Question no 3667 : MRP for PP

In SAP PP as at ECC6.0 EhP6, which of the following is the setting for MRP run when the system first looks for a Routing, if Routing was not found, it will then revert to check either the Lot Size dependent data or Lot Size independent data in the Material Master ?

(only one answer)

A)  Basic date scheduling.
B)  Detail date scheduling.
C)  Routing date scheduling.
D)  3 stage date scheduling.
E)  Lead time scheduling.
.

Answer: E

Lead time scheduling.

Wednesday, October 23, 2019

Question no 3666 : Enterprise Structure in MM

In SAP MM as at ECC6.0 EhP7, which of the following in not assigned to the Enterprise Structure ?

(only one answer)

A)  Plant.
B)  Storage Location.
C)  Purchasing Organization.
D)  Purchasing Group.
E)  Company Code.
.

Click "1 comment" to view suggested answers

Wednesday, October 16, 2019

Question no 3665 : External Services

In SAP MM as at ECC6.0 EhP6, which of the following can use External Services with Service Masters ?

(more than one answers)

A)  Production Order.
B)  Maintenance Order.
C)  Service Order.
D)  Network Order.
E)  Purchase Order.
.

click the "1 comment" to show suggested answers

Wednesday, October 9, 2019

Question no 3664 : Maintenance Notification

In SAP PM as at ECC6.0 EhP6, which of the following is not true about a Maintenance Notification ?

(more than one answers)

A)  It can be assigned to a PM Order to collect costs.
B)  It can be generated via Saving a Maintenance Order.
C)  It can be assigned with one or more General Task List.
D)  It can be created without a reference Object.
E)  It can be closed without converting to a Maintenance Order.
.

Click on "1 comment:" for suggested answer

Wednesday, October 2, 2019

Question no 3663 : Sampling Procedure with different Lot Sizes

In SAP QM as at ECC6.0 EhP6, to achieve sample size for different lot size ranges, which of the following is necessary ?

(only one answer)

A)  Sampling Scheme.
B)  Dynamic Modification.
C)  Inspection Type activated in the IMG.
D)  Inspection Lot Document Type activated in the IMG.
E)  Material Specification.
.

Answer: A

Tuesday, October 1, 2019

Wednesday, September 25, 2019

Question no 3662 : Estimated Cost

In SAP PM as at ECC6.0 EhP6, Cost Estimate in the Maintenance Order is entered via ?

(only one answer)

A)  Value Category.
B)  Cost Element.
C)  Cost Element Group.
D)  Costing Variant.
E)  Valuation Variant.
.

Answer: A

Question no 3661 : Cumulative Capacity Requirement

In SAP PP as at ECC6.0 EhP6, which of the following allows views of Capacity Requirements for multiple Work Centers ?

(only one answer)

A)  Work Center Hierarchy.
B)  Work Center Grouping.
C)  Work Center Structure.
D)  Work Center Link.
E)  Work Center List.
.

Answer: A