Question no 3662 : Estimated Cost
In SAP PM as at ECC6.0 EhP6, Cost Estimate in the Maintenance Order is entered via ?
(only one answer)
A) Value Category.
B) Cost Element.
C) Cost Element Group.
D) Costing Variant.
E) Valuation Variant.
.
Answer: A
(only one answer)
A) Value Category.
B) Cost Element.
C) Cost Element Group.
D) Costing Variant.
E) Valuation Variant.
.
Answer: A
Monday, September 23, 2019
Saturday, September 21, 2019
Thursday, September 19, 2019
Wednesday, September 18, 2019
Question no 3661 : Cumulative Capacity Requirement
In SAP PP as at ECC6.0 EhP6, which of the following allows views of Capacity Requirements for multiple Work Centers ?
(only one answer)
A) Work Center Hierarchy.
B) Work Center Grouping.
C) Work Center Structure.
D) Work Center Link.
E) Work Center List.
.
Answer: A
(only one answer)
A) Work Center Hierarchy.
B) Work Center Grouping.
C) Work Center Structure.
D) Work Center Link.
E) Work Center List.
.
Answer: A
Monday, September 16, 2019
Sunday, September 15, 2019
Thursday, September 12, 2019
Wednesday, September 11, 2019
Question no 3660 : Goods Receipt Time
In SAP MM as at ECC6.0 EhP6, which of the following is TRUE when Goods Receipt Processing Time is Zero in the Material Master MRP2 data view ?
(only one answer)
A) Goods Receipt Date = Stock Available Date.
B) Opening Date = Order Start Date.
C) Order Start Date = Goods Receipt Date.
D) Exception Message created at MRP run.
E) System will use the Plant Parameter Goods Receipt Time.
.
Answer: A
(only one answer)
A) Goods Receipt Date = Stock Available Date.
B) Opening Date = Order Start Date.
C) Order Start Date = Goods Receipt Date.
D) Exception Message created at MRP run.
E) System will use the Plant Parameter Goods Receipt Time.
.
Answer: A
Monday, September 9, 2019
Saturday, September 7, 2019
Thursday, September 5, 2019
Wednesday, September 4, 2019
Question no 3659 : Purchasing Info Record
In SAP MM as at ECC6.0 EhP6, which of the following are possible for the creation of a Purchasing Info Record ?
(more than one answers)
A) It can be created without a Plant.
B) It can be created with a One-Time Vendor.
C) It can be created without a Material.
D) It can be created without a Purchasing Organization.
E) It can be created with a Material Group.
.
Answers: A, C, E
The following are possible:
. Vendor must be permanent vendor and not a One-Time Vendor.
. Plant or without Plant is possible.
. Purchasing Organization is mandatory.
. Material or without Material is possible.
. In-Case without Material then material Group is necessary.
(more than one answers)
A) It can be created without a Plant.
B) It can be created with a One-Time Vendor.
C) It can be created without a Material.
D) It can be created without a Purchasing Organization.
E) It can be created with a Material Group.
.
Answers: A, C, E
The following are possible:
. Vendor must be permanent vendor and not a One-Time Vendor.
. Plant or without Plant is possible.
. Purchasing Organization is mandatory.
. Material or without Material is possible.
. In-Case without Material then material Group is necessary.