In SAP PM as at ECC6.0 EhP6, which of the following are characteristics of a Strategy Plan ?
(only one answer)
A) A Strategy must be assigned to the Equipment Master.
B) A Strategy must be assigned to the Functional Location.
C) A Strategy must be assigned to the General Task List.
D) A Strategy must be assigned to the Plant Parameter.
E) A Strategy must be assigned to the Maintenance Plan Category.
.
Answer: C
The Strategy for the General Task List must match the Maintenance Plan Header's Strategy.
(only one answer)
A) A Strategy must be assigned to the Equipment Master.
B) A Strategy must be assigned to the Functional Location.
C) A Strategy must be assigned to the General Task List.
D) A Strategy must be assigned to the Plant Parameter.
E) A Strategy must be assigned to the Maintenance Plan Category.
.
Answer: C
The Strategy for the General Task List must match the Maintenance Plan Header's Strategy.