Question no 3529 : UD Stock Posting options
In SAP QM as at ECC6.0 EhP6, which of the following options are available at UD posting ?
(more than one answers)
A) Un-Restricted.
B) Scrap.
C) Block stock.
D) GR-Blocked Stock.
E) Return Delivery to vendor.
.
(more than one answers)
A) Un-Restricted.
B) Scrap.
C) Block stock.
D) GR-Blocked Stock.
E) Return Delivery to vendor.
.
Tuesday, March 27, 2018
Question no 3528 : Material Master Inspection Type Detail
In SAP QM as at ECC6.0 EhP6, which of the following can be assigned to the Inspection Type Detail in the Material Master data QM data view ?
(more than one answers)
A) Sampling Procedure.
B) Sampling Scheme.
C) Dynamic Modification Factor.
D) Sampling Percentage.
E) 100% Sampling.
.
Answer: C, D, E
Review MM02 for a material with QM view's inspection type detail screen~!
Sunday, March 25, 2018
Saturday, March 24, 2018
Friday, March 23, 2018
Thursday, March 22, 2018
Question no 3527 : Dynamic Modification assignment
In SAP QM as at ECC6.0 EhP6, in which of the following you cannot assign the Dynamic Modification rule ?
(more than one answers)
A) Inspection Plan header.
B) Inspection Plan operations.
C) Inspection Plan operation's Master Inspection Characteristics.
D) Material Master QM data view.
E) Material Master QM data view's Inspection Type detail.
.
Answer: B, D
Dynamic Modification is assigned to
1. Material Master QM data view's Inspection Plan detail screen.
2. Inspection Plan Header screen.
3. Inspection Plan operation's MIC.
(more than one answers)
A) Inspection Plan header.
B) Inspection Plan operations.
C) Inspection Plan operation's Master Inspection Characteristics.
D) Material Master QM data view.
E) Material Master QM data view's Inspection Type detail.
.
Answer: B, D
Dynamic Modification is assigned to
1. Material Master QM data view's Inspection Plan detail screen.
2. Inspection Plan Header screen.
3. Inspection Plan operation's MIC.
Wednesday, March 21, 2018
Question no 3526 : Sample Size determination criterion
In SAP QM as at ECC6.0 EhP6, which of the following are influencing factors for the determination of the Sample Size for an Inspection Lot ?
(more than one answer)
A) Purchasing Info Record.
B) Sampling Scheme.
C) Dynamic Modification Factor.
D) Sampling Procedure.
E) Storage Condition.
.
Answer: B, C, D
You can assign Sampling Procedure w/o Sampling Scheme and the sample size can be Percentage or Fixed or 100%.
You can assign Sampling Procedure with Sampling Scheme where a Table of sample size is determined by the incoming lot sizes.
You can also use Sampling Procedure with Sampling Scheme & Dynamic Modification Rule to influence the choice of Severity based on the Quality Level and hence the sample size from the Sampling Scheme.
(more than one answer)
A) Purchasing Info Record.
B) Sampling Scheme.
C) Dynamic Modification Factor.
D) Sampling Procedure.
E) Storage Condition.
.
Answer: B, C, D
You can assign Sampling Procedure w/o Sampling Scheme and the sample size can be Percentage or Fixed or 100%.
You can assign Sampling Procedure with Sampling Scheme where a Table of sample size is determined by the incoming lot sizes.
You can also use Sampling Procedure with Sampling Scheme & Dynamic Modification Rule to influence the choice of Severity based on the Quality Level and hence the sample size from the Sampling Scheme.
Tuesday, March 20, 2018
Monday, March 19, 2018
Sunday, March 18, 2018
Question no 3525 : Service Condition with Plant
In SAP MM as at ECC6.0 EhP6, ML33 Service Condition with Plant requires which of the following entries ?
(more than one answers)
A) Purchasing Organization.
B) Vendor.
C) Plant.
D) Service Master.
E) Purchasing Group.
.
Answer: A, B, C, D
ML33 t-code, check yourself.
(more than one answers)
A) Purchasing Organization.
B) Vendor.
C) Plant.
D) Service Master.
E) Purchasing Group.
.
Answer: A, B, C, D
ML33 t-code, check yourself.
Saturday, March 17, 2018
Thursday, March 15, 2018
Wednesday, March 14, 2018
Tuesday, March 13, 2018
Question no 3524 : External Services data structure
In SAP PM as at ECC6.0 EhP6, which of the following must be at Plant dependent for External Services ?
(only one answer)
A) Service Master.
B) Model Service Specification.
C) Standard Service Catalog.
D) Service Condition.
E) None of the above.
.
Answer: E
AC03, ML10, ML01 Service Master, MSS, SCC all w/o Plant
ML45, ML39 condittions without Plant
ML33 is condition with Plant
(only one answer)
A) Service Master.
B) Model Service Specification.
C) Standard Service Catalog.
D) Service Condition.
E) None of the above.
.
Answer: E
AC03, ML10, ML01 Service Master, MSS, SCC all w/o Plant
ML45, ML39 condittions without Plant
ML33 is condition with Plant
Monday, March 12, 2018
Question no 3523 : Subcontracting Movement
In SAP Material Management as at ECC6.0 EhP6, which of the following are Logistics and Accounting Features of Subcontracting Process flow ?
(more than one answers)
A) When Parts belong to us are transferred to the contractor, no accounting documents are posted.
B) Subcontracting stock is represented by special stock "O".
C) ME2O allow both transfer of parts to the contractor as well as receiving completed assemblies.
D) ME2O allow both transfer via MM and SD Delivery.
E) The Purchasing Order for Subcontracting should contain the parts to be transferred if it were to be transferred via ME2O.
.
(more than one answers)
A) When Parts belong to us are transferred to the contractor, no accounting documents are posted.
B) Subcontracting stock is represented by special stock "O".
C) ME2O allow both transfer of parts to the contractor as well as receiving completed assemblies.
D) ME2O allow both transfer via MM and SD Delivery.
E) The Purchasing Order for Subcontracting should contain the parts to be transferred if it were to be transferred via ME2O.
.
Sunday, March 11, 2018
Friday, March 9, 2018
Question no 3522 : Maintenance Activity Type
In SAP PM as at ECC6.0 EhP6, the default of the Maintenance Activity Type to the Maintenance Order is via which of the following ?
(Only one answer)
A) Order Type.
B) Order Type + Planning Plant.
C) Planning Plant.
D) Order Type + Planner Group.
E) Order Type + Planning Plant + Planner Group.
.
(Only one answer)
A) Order Type.
B) Order Type + Planning Plant.
C) Planning Plant.
D) Order Type + Planner Group.
E) Order Type + Planning Plant + Planner Group.
.
Thursday, March 8, 2018
Question no 3521 : Service Category in Service Master
In SAP MM as at ECC6.0 EhP6, the Service Category for creating the Service Master have the following features ?
(more than one answers)
A) Assignment of Account Category Reference for Valuation Class selections.
B) Allow both Internal and External Number Range for each Service Category.
C) Field Selection.
D) Pricing Control default.
E) Plant assignment.
.
(more than one answers)
A) Assignment of Account Category Reference for Valuation Class selections.
B) Allow both Internal and External Number Range for each Service Category.
C) Field Selection.
D) Pricing Control default.
E) Plant assignment.
.
Wednesday, March 7, 2018
Tuesday, March 6, 2018
Monday, March 5, 2018
Question no 3520 : MEB features
In SAP PM as at ECC6.0 EhP6, which of the following features are correctly depicting the MEB functionality ?
(more than one answers)
A) More than one Notifications can be assigned to a Revision in MEB.
B) Only one Notification can be assigned to a Revision in MEB.
C) Only Notification with Hierarchy Task List can be assigned to the Revision in MEB.
D) Notifications with or without Hierarchy Task List can be assigned to the Revision in MEB.
E) A Notification with an Order can be assigned to a Revision in MEB.
.
Answer: A, D, E
A, B) 1 or more Notification can be assigned to a Revision in MEB.
C, D) Notifications with or without Hierarchy can be assigned to a Revision in MEB.
(more than one answers)
A) More than one Notifications can be assigned to a Revision in MEB.
B) Only one Notification can be assigned to a Revision in MEB.
C) Only Notification with Hierarchy Task List can be assigned to the Revision in MEB.
D) Notifications with or without Hierarchy Task List can be assigned to the Revision in MEB.
E) A Notification with an Order can be assigned to a Revision in MEB.
.
Answer: A, D, E
A, B) 1 or more Notification can be assigned to a Revision in MEB.
C, D) Notifications with or without Hierarchy can be assigned to a Revision in MEB.
Sunday, March 4, 2018
Question no 3519 : MEB with Project
In SAP PM as at ECC6.0 EhP6, which of the following method is used to ensure the Maintenance Orders are automatically assigned to the Network Activities in MEB ?
(more than one answers)
A) Ref PM/PS Element at the Task List Header.
B) Ref PM/PS Element at the Task List Operations.
C) Ref PM/PS Element at the Task List WBS.
D) Ref PM/PS Element at the Task List Network Activity.
E) Ref PM/PS Element at the Task List Revision Header.
.
Answer: A, D
Task Lit Header's + Network Activity must have matching Ref PM/PS Element.
(more than one answers)
A) Ref PM/PS Element at the Task List Header.
B) Ref PM/PS Element at the Task List Operations.
C) Ref PM/PS Element at the Task List WBS.
D) Ref PM/PS Element at the Task List Network Activity.
E) Ref PM/PS Element at the Task List Revision Header.
.
Answer: A, D
Task Lit Header's + Network Activity must have matching Ref PM/PS Element.
Friday, March 2, 2018
Thursday, March 1, 2018
Question no 3518 : PM Alternative Labeling System
In SAP PM as at ECC6.0 EhP6, the following are applicable for Alternative Labeling System EXCEPT ?
(more than one answers)
A) Functional Location.
B) Reference Functional Location.
C) Equipment.
D) Reference Equipment.
E) Measuring Point.
.
Answer: B, C, D, E
Only FL can use Alternative Labeling System.
(more than one answers)
A) Functional Location.
B) Reference Functional Location.
C) Equipment.
D) Reference Equipment.
E) Measuring Point.
.
Answer: B, C, D, E