WM SCM630 Data Prep

Data preparation for staging method in PP

Unit 06 Exercise 21 SD Two-Step Picking

1. Prepare Sales Order (VA01) and Delivery Order (VL01N)
    Ship-to-Party 1000 Sales Area 1000/10/00
    SO1 item 1 T-BW04-## 1
           item 2 T-BW05-## 2
    SO2 item 1 T-BW04-## 1
    SO3 item 1 T-BW05-## 1

    Perform full Delivery for all 3 SO
    Note down all 3 SO and all 3DO
       
Unit 08 Exercise 26 PP WM Staging

1. MM01 extend WM view for T-BW01-## into Plant 1000 Warehouse 1##
    WM2 view SUT 20 pc E1

2. Switch OPKP to 'X' (TR on Release) in IMG for Prod Scheduler Profile

3. LPK1 Control Cycle for Pick list item
    Material T-BW02-##, T-BW03-##, T-BW04-##, T-BW05-##
    Supply Area PVB 13101##
    Staging indicator 1 (Pick list item), dynamic Bin

4. Check LS41
    T-BW01-## / PROD-1310 storage Bin / Staging indicator 2 'Create Part'
    T-BW02-## / Dynamic Bin / Staging indicator 1 'Pick List item'
    T-BW03-## / Dynamic Bin / Staging indicator 1 'Pick List item'
    T-BW04-## / Dynamic Bin / Staging indicator 1 'Pick List item'
    T-BW05-## / Dynamic Bin / Staging indicator 1 'Pick List item'
    T-BW06-## / PROD-1310 storage Bin / Staging indicator 3 'Release Order Part'
    T-BW07-## / PROD-1310 storage Bin / Staging indicator 3 'Release Order Part'  

Thursday, February 25, 2016

Question no 3096 : By-Product and Co-Product

In SAP PPPI as at ECC6 EhP6, which of the following statements correctly describes the setting up of By-Product and Co-Product ?

(More than one answers)

A)  By-Product material is indicated by the 'By-Product' indicator in MRP2 data view.
B)  Co-Product material is indicated by the 'Co-Product' indicator in MRP2 data view.
C)  By-Product material require 'Joint Production' setting in the material master.
D)  Co-Product material require 'Joint Production' setting in the material master.
E)  Both By-Product and Co-Product require a negative quantity when assigned to the BOM.
.

Saturday, February 20, 2016

Question no 3095 : Co-Product for Process Order

In SAP ERP as at ECC6.0 EhP7, the Pre-requisite for Co-Product activation for Process Orders are which of the following ?

(more than one answers)

A)    Co-Product indicator in the MRP 2 data view.
B)    Co-Product indicator when the Co-Product is assigned to the Phase operation in the Recipe.
C)    Backflushing inidcator when the Co-Product is assigned to the Phase operation in the Recipe.
D)    Joint-Production costing setup for the Co-Products.
E)    Price search strategy and apportionment structure in the Costing Variant for the Co-Product Costing.

Friday, February 19, 2016

Question no 3094 : X-Steps and Process Instruction

In SAP PP-PI as at ECC6.0 EhP6, which of the following setting 'locks-in' whether X-Steps and/or Process Instructions are allowed for the Master Recipe ?

(only one answer)

A)   Routing usage.
B)   Default value profile.
C)   Plant parameter.
D)   Production version.
E)   Production scheduler profile.

Wednesday, February 17, 2016

Question no 3093 : Means of Production in PPPI

In SAP PP-PI, the Means of production involved in a production process that have capacities assigned to them is called a _______________.

(only one answer)

A)   Work Center.
B)   Processing Unit
C)   Resource.
D)   Plant.
E)   Labor.