Question no 1581 : Purchase Requisition in Maintenance Order

In SAP PM, which of the following scenarios results in Purchase Requisition generated in the Maintenance Order ?

(more then one answers)

A)    Item Category "R" for components.
B)    Item Category "N" for components.
C)    Control Key "PM02" for operations.
D)    Control Key "PM03" for operations.
E)    Control Key "PM05" for operations.
.

Wednesday, May 30, 2012

Question no 1580 : Maintenance Plan Planning Data

In SAP PM, which of the following planning data cannot be defaulted from the Technical Object entered in the Maintenance Plan ?

(more then one answers)

A)     Planning Plant and Planner Group.
B)     Maintenance Work Center.
C)     Order type.
D)     Priority.
E)     Maintenance Activity Type.
.

Question no 1579 : Single Cycle Maintenance Plan

In SAP PM, which of the following are not mandatory entries in a Single Cycle Maintenance Plan where the call object is a maintenance order ?

(more then one answers)

A)     Maintenance Strategy.
B)     Maintenance Task List.
C)     Technical Objects.
D)     Maintenance Order type.
E)     Counter.
.

Monday, May 28, 2012

Question no 1578 : Maintenance Plan

In SAP PM, what are the possible call objects from the scheduling of a Maintenance Plan which can be configured to the Maintenance Category ?

(more then one answers)

A)     Maintenance Notification.
B)     Maintenance Order.
C)     Purchase Requisition.
D)     Purchase Order.
E)     Service Entry Sheet.
.

Friday, May 25, 2012

Question no 1577 : Maintenance Task List in Maintenance Plan

In SAP PM, what are the options for use or selection of the maintenance task list in the Maintenance Plan ?

(more then one answers)

A)    You can create new Maintenance Task list in the Maintenance Plan while creating the Maintenance item.
B)    You can choose or select from existing Maintenance Task list in the Maintenance item.
C)    You can ignore and not include a Maintenance Task list in the Maintenance item of the Maintenance Plan.
D)    You can include one Maintenance Task list in the Maintenance plan header to be used for all Maintenance Items.
E)    You can include either a suitable Equipment Task list or Functional Location Task list or General Task list in the Maintenance item.
.

Thursday, May 24, 2012

Question no 1576 : ADSUBCON for PM

In SAP PM ECC6.0, the transaction code ADSUBCON for processing the subcontracting of the refurbishment scenario, which of the following are supported by that transaction ?

(more then one answers)

A)     Transfer of refurbishment material to the subcontractor via MB1B or MIGO.
B)     Creating of the Purchase Requisition for the subcontracting scenario.
C)     Converting the Subcontracting Purchase Requisition to Purchase Order.
D)     Transfer of refurbishment material to the subcontractor via SD Delivery.
E)     Goods receipt of the Purchase Order to receive the return of the completed refurbish material.
.

Wednesday, May 23, 2012

Question no 1575 : Subcontracting Refurbishment

In SAP PM ECC6.0, the following statements describes the features and functions of subcontracting the refurbishment process, select statements which are correct about it ?

(more then one answers)

A)    Only the standard  SAP provided Order type PM04 can be used for the maintenance order creation of this scenario, no specific configuration is required. 
B)    An MM purchase info record with subcon category should be created for the subcon services charges.
C)    The material (equipment) will be transferred to the subcontractor and seen as special stock type "O".
D)    Transaction IW8W will be used to receive the completed refurbished material (equipment).
E)    Item Category "L" is registered in the Purchase Documents for this scenario.
.

Tuesday, May 22, 2012

PP Event-Driven Kanban

Click on any slide to see presentation in Slide-Show version



























Monday, May 21, 2012

Question no 1574 : PM02 and PM03 differences in Plant Maintenance

In SAP PM the differences between use of PM02 and PM03 for external maintenance work procurement in the Maintenance Order are the following except ?

(more then one answers)

A)    The same Item Category is used in both types of Purchase Documents.
B)    A different Account Assignment is used in the Purchase Documents.
C)    Completion of the approved services done are always represented by a Material document.
D)    Both scenario can perform invoice verification with reference to Service Entry Sheet.
E)    In Both scenario, Purchase Requisition or Purchase Order can be created before the Maintenance order is Released. 
.

Sunday, May 20, 2012

Question no 1573 : PM02 and PM03 in Plant Maintenance

In SAP PM, what are the similarities of control key PM02 and PM03 used for external procurement of maintenance services in Plant Maintenance ?

(more then one answers)

A)    Both uses the goods receipts (MIGO) transaction to complete the services.
B)    Both uses the same account assignment object indicator in the Purchase Requisition.
C)    Both uses invoice verification transaction (MIRO) to complete the invoice entry.
D)    Both do not require a work center entry in the operation concerned.
E)    Both will update the maintenance order "GMPS" system status upon completion of the services.
.

Saturday, May 19, 2012

Question no 1572 : External Services in Plant Maintenance

In SAP PM, when will the system update the Maintenance Operation of Control Key "PM03" (External Services Procurement) to system status of "EOPD" ?

(only one answer)

A)    When the External Services Purchase Requisition is created.
B)    When the External Services Purchase Order is created.
C)    When the External Services Operations in the Maintenance Order is Released.
D)    When the External Services Purchase Order's Service Entry Sheet is entered.
E)    When the External Services Purchase Order's Service Entry Sheet is approved.
.

Friday, May 18, 2012

Question no 1571 : PM Work Center

In SAP PM, the Maintenance Work Center created must be _____________________.

(only one answer)

A)    Created for the Planning Plant.
B)    Created with the necessary Standard Value Keys.
C)    Created with the work center category with Application "I" for Plant Maintenance.
D)    Created with the number range provided in Plant Maintenance customization.
E)    Created with the correct validity period.
.

Thursday, May 17, 2012

Question no 1570 : Internal number assignment in PM

In SAP PM, which of the following objects do not have internal number assignment possibility ?

(more then one answers)

A)    Functional Location.
B)    Work Center.
C)    Class Characteristics.
D)    Measuring Point.
E)    Material Master PRT.
.

Wednesday, May 16, 2012

Question no 1569 : Number range in Plant Maintenance

In SAP PM, which of the following objects in SAP Plant Maintenance allows internal number assignment ?

(more then one answers)

A)    Functional Location.
B)    Measuring Point.
C)    Measuring Document.
D)    Equipment.
E)    Work Center.
.

Monday, May 14, 2012

Question no 1568 : Common assignment to Technical Objects

In SAP PM, which of the following can be assigned to both Equipment and Functional Location ?

(more then one answers)

A)    Warranty Master.
B)    Serial number.
C)    Construction Type.
D)    Permit.
E)    Class.
.