Question no 1024 : Service Packages in Maintenance Task List

In SAP PM, which of the following can be assigned in a Service Package ?

(only one answer)

A)       Material Master.
B)       Service Master.
C)       PRT.
D)       Material Master with a material type for services.
E)       Maintenance Strategy.
.

Wednesday, March 30, 2011

Question no 1023 : Maintenance Task List concepts

In SAP PM, about Maintenance Task List, which of the following are not true ?

(more then one answers)

A)      Maintenance Packages are only available for General Task List, and not for Equipment of Functional Location Task List.
B)      Service Packages are available only for control key PM02 and PM03 for all types of Maintenance Task List.
C)      All Maintenance Task list types will have internal and external number ranges for the Group number.
D)      There are no number ranges assignment for the Group counters.
E)      A General Task List can be assigned to several Equipments.
.

Tuesday, March 29, 2011

Question no 1022 : Maintenance Task List Header

In SAP PM, which of the following is true about General Maintenance Task List ?

(more then one answers)

A)      It can have either internal or external number for the Group number.
B)      The group counter can be an alphanumeric entry.
C)      The group counter can be either alphanumeric or numeric entry.
D)      A valid usage and status is mandatory for Task List selection.
E)      Multiple materials can be assigned to the Task List header.
.

.

Monday, March 28, 2011

Question no 1021 : Maintenance Task list operations

In SAP PM, which of the following statement is not true about component assignment to a maintenance operations in a maintenance task list ?

(more then one operations)

A)      When manually entering a component to an operation, you can enter the item category "L" for Stock material or "N" for non-stock.
B)       The same component several times to one operation.
C)       A component entered in an operation cannot be repeated its assignment again in another operation.
D)       Only item category "L" is allowed for manual entry of component to an operation.
E)        A non-stock material can be selected from the structure list into the component screen of an operation.
.

Sunday, March 27, 2011

Question no 1020 : Component assignment in Task List

In SAP PM, which of the following techniques are available to add or assign components to an operation in the maintenance task list ?

(more then one answers)

A)     via Structure list.
B)      via Structure graphics.
C)      via Internet Catalog.
D)      via Manual entry.
E)       via Service Package.
.
.

Thursday, March 24, 2011

Question no 1019 : Create with reference in PM BOM Categories

In SAP PM, which of the following of BOM creation reference is possible ?

(more the one answers)

A)     Create Functional Location BOM with reference to Material BOM.
B)     Create Functional Location BOM with reference to Equipment BOM.
C)     Create Equipment BOM with reference to Material BOM.
D)     Create Material BOM with reference to Functional Location BOM.
E)     Create Material BOM with reference to Equipment BOM.
.

Monday, March 21, 2011

Question no 1018 : Item Status in Bills of Material

In SAP, the item status of "Plant maintenance" in the BOM item detail is controlled by which of the following parameter ?

(only one answer)

A)    Item Category.
B)    BOM header Usage.
C)    BOM header Status.
D)    Order type.
E)    BOM Category.
.

Sunday, March 20, 2011

Question no 1017 : Synchronization of Equipment and Serial

In SAP PM, when the equipment number created is synchronized to the serial number, this means which setting has been done ?

(only one answer)

A)    The equipment category contains the synchronization setting.
B)     The serial profile assigned to the material number contains the synchronization's setting.
C)     During goods receipt, the synchronization setting is selected.
D)     A configuration is done at the Plant Parameter in customizing.
E)     The serial level in the material is set to ensure synchronization.
.

Saturday, March 19, 2011

Question no 1016 : AVLB System Status of Equipment

In SAP PM, when the equipment is when with a serial number and contain a system status "AVLB", this means _____________________________ .

(only one answer)

A)     The equipment is available as Warehouse Stock.
B)     The equipment is available through a Purchase Order which is outstanding.
C)     The equipment is available for installation as it is already goods issued from the Warehouse.
D)     The equipment is available as Warehouse Stock and ready for installation.
E)     The equipment is available, and calibrated, in the Warehouse Stock.
.

Friday, March 18, 2011

Question no 1015 : PM Master Data

In SAP PM, which of the following statements are true about PM master data ?

(more then one answers)

A)      the serial number can be equal to the equipment master number.
B)      the serial number must be equal to the equipment master number.
C)      the serial number need not be equal to the equipment master number.
D)      only one serial number can be assigned to at equipment master number.
E)      a serial number profile is mandatory for a material of a equipment to be managed by a serial number.
.

Thursday, March 17, 2011

Question no 1014 : Serial Profile

In SAP PM, which of the following are true about Serial Profile ?

(more then one answers)

A)      It determine synchronization of serial number and equipment number.
B)      It determine synchronization of asset number, serial number, and equipment number.
C)      It determine equipment category to used to create equipment in goods receipt of purchase order.
D)      It determine serial number requirement in selected logistics processes.
E)      It determine construction type material to be equal to serial material.
.

Monday, March 14, 2011

Question no 1013 : Maintenance Task List

In SAP PM, which of the following are possible PRTs that can be assigned to a maintenance operation ?

(more then one answer)

A)      Material PRT.
B)      Document PRT.
C)      Equipment PRT.
D)      Miscellaneous PRT.
E)      Measuring Point.
.

Question no 1012 : Structure of a Maintenance Plan

In SAP PM, which of the following is true about a Maintenance Plan ?

(more then one answers)

A)     A maintenance plan can have several maintenance items.
B)      A maintenance item can have several technical objects.
C)      A maintenance plan can have only one maintenance task list.
D)      Each maintenance item can have several maintenance task list.
E)      Each maintenance item in the maintenance plan can have its own maintenance cycle.
.

Sunday, March 13, 2011

Question no 1011 : Capacity in Maintenance Order

In SAP PM, when the capacity requirement or capacity load for a work center in a maintenance order released or removed ?

(more then one answers)

A)      when a maintenance order is technically completed.
B)      when the operation for the work center is set "final confirmation".
C)      when the operation for the work center is deleted from the maintenance order.
D)      when all the components assigned to the operations of the work center is finally issued.
E)      when the maintenance order is set with a "LKD" or locked status.
.

Question no 1010 : IWBK

In SAP PM, the transaction code IWBK for Material Availability List allows you to do which of the following ?

(more then one answers)

A)     Check whether goods receipt of externally processed operations via a Purchase Order is completed.
B)     Check whether confirmation of an internal operations is completed.
C)     Check whether goods receipt of a non-stock material via a Purchase Order is completed.
D)     Check whether purchase order has been created for a non-stock material purchase requisition.
E)     Check whether purchase order of a stock material is completed.
.

Saturday, March 12, 2011

Question no 1009 : Catalog types for maintenance notification

In SAP PM, which of the following are standard catalog types for maintenance notification ?

(more then one answer)

A)      Object part.
B)      Usage decision.
C)      Damage.
D)      Attributes.
E)      Cause.
.

Question no 1008 : Maintenance order technical completion

In SAP PM, when a maintenance order to technically completed, it may also be closing the notification provided that ______________________ .

(only one answer)

A)      All the task and activities are also set to be completed.
B)      All the activities are completed.
C)      There is no breakdown indicator in the maintenance notification.
D)      All the tasks are completed.
E)      The Notification type allows completion via technical completion of a maintenance order.
.

Friday, March 11, 2011

Question no 1007 : Maintenance Order-Notification

In SAP PM, when a break-down maintenance order is to be created, it should also automatically generated a maintenance notification when the order is saved. Which of the following parameter is used to achieve this scenario ?

(only one answer)

A)      Notification type at Client level.
B)      Notification type at Plant level.
C)      Order type at Client level.
D)      Order type at Plant level.
E)      User exit.
.

Question no 1006 : Maintenance Notification System Status

In SAP PM Notification, if the Notification has the following status ATCO and ORAS; this would mean which of the following ?

(only one answer)

A)     Task Outstanding and Order Completed.
B)     All Task Completed and Order Completed.
C)     All Task Completed and Order Assigned.
D)     Task Outstanding and Order Assigned.
E)     Task Outstanding and Order Technically Completed.
.

Thursday, March 10, 2011

Question no 1005 : Calculate available capacity for work center

In PM, a work center contains the following, and please calculate the available capacity ?

Start time : 09:00
Finish time : 18:00
Length of break : 01:30
Capacity Utilization: 90
No. of individual capacity : 5

(only one answer)

A)     33
B)      22.75
C)      33.75
D)      12.75
E)       34
.

Question no 1004 : PM Organization

In SAP PM, which of the following organization concepts are correct ?

(more then one answers)

A)     A logistics plant when created, it is also behave as a maintenance plant.
B)     Multiple maintenance planning plants can be assigned to a maintenance plant.
C)     A maintenance plant can be used as an organization for spare parts storage.
D)     Multiple planner groups can be assigned to a maintenance planning plant.
E)     A maintenance plant can only have one maintenance work center.
.

Wednesday, March 9, 2011

Question no 1003 : Purpose of Maintenance Plant

In SAP PM, the purpose of a Maintenance Plant can play which of the following role in a plant maintenance environment ?
(more then one answers)

A)     Location of Technical Object.
B)     Maintenance Work Center.
C)     Storage for spare parts.
D)     Assignment of Functional Locations.
E)     Assignment of Permits.
.

Question no 1002 : User Interfaces in SAP

In future, there will be a unified interface combining the advantages of SAPGUI and the portal; one initial approach is the ____________________ .

(only one answer)

A)     NetWeaver Business Client.
B)      Role-based menu.
C)      HTML-based access.
D)      Single-Point entry.
E)      NetWeaver Role-base.
.

Tuesday, March 8, 2011

Question no 1001 : Text types in MM

Which of the following objects text types can be configured for new text types ?

(more then one answer)

A)      Material Master.
B)      Vendor Master.
C)      Purchasing Info Record.
D)      Purchase Requisition.
E)      Purchase Order.
.

Question no 1000 : Factory Calender

In SAP, which of the following statements are true about Factory Calender ?

(more then one answers)

A)      A public holiday can be assigned to multiple public holiday calendars.
B)      A public holiday calendar can be assigned to multiple plants.
C)      A plant can be assigned with multiple public holiday calendars.
D)      Public holidays assigned in a public holiday calendar can be time dependent.
E)      The public holiday calendar itself is also time dependent.
.

Monday, March 7, 2011

Question no 999 : Account Assignment and Item Category in MM

In SAP MM, the combination of Account Assignment and Item Category possibility in a Purchasing Document is configured at which organizational level ?

(only one answer)

A)      Plant level.
B)      Purchasing Organization level.
C)      Plant and Purchasing Organization level.
D)      Plant, Purchasing Organization, and Document type level.
E)      None of the above.
.

Question no 998 : Field Selection for Purchasing Document

In SAP MM, in order to control the field selection during Release Strategy Processes; this can be achieved via which of the following configuration parameters ?

(only one answer)

A)      Item category.
B)      Document type.
C)      Transaction.
D)      Price display authorization.
E)      Release Status
.

Sunday, March 6, 2011

Question no 997 : Overall Release in MM Purchasing Docuement

In SAP MM, which of the following Purchasing Document Type configuration has the "Overall Release" configuration option for Release Strategy ?

(only one answer)

A)      Purchase Requisition.
B)      RFQ.
C)      Purchase Order.
D)      Contract.
E)      Scheduling Agreement.
.

Question no 996 : Number Range in MM

In SAP MM, which of the following objects be assigned to have both internal and external number range for a single object ?

(more then one answers)

A)     Material type.
B)      Vendor Account group.
C)      Purchasing Document type.
D)      Material Document type.
E)      MRP Plant Parameter for Planned Orders.
.

Saturday, March 5, 2011

Question no 995 : Non-Stock scenario without material account determination

In SAP MM Account Determination, the Consumption G/L account for scenario of Purchase Order with Consumable Scenario without material is determined via ____________________ .

(only one answer)

A)      GBB Transaction Event Key and Valuation class assigned to Material type.
B)       BSX Transaction Event Key and Valuation class assigned to Material group.
C)       GBB Transaction Event Key and Valuation class assigned to Material group.
D)       BSX Transaction Event Key and Valuation class assigned to Material type.
E)       GBB Transaction Event Key and Valuation class assigned to Account Category Reference.
.

Question no 994 : Valuation Class Assignment

In SAP MM, You can directly assigned the Valuation Class to which of the following ?

(more then one answers)

A)    Material group.
B)     Account group.
C)     Material type.
D)     Account Category reference.
E)     Account Assignment Category.
.

Friday, March 4, 2011

Question no 993 : Modifier in Account Determination

In SAP MM Account Determination, the "Modifier" or "Account Grouping" can be assigned to which object for the purpose of Consumable Procurement Scenario ?

(only one answer)

A)    Material type.
B)     Account group.
C)     Valuation grouping code.
D)     Valuation class.
E)      Account Assignment Key.
.

Question no 992 : Value String Identification

In SAP MM Account Determination, which of the following value String is used for Purchase Order with Account Assignment ?

(only one answer)

A)     WA01.
B)      WE01.
C)      WA14.
D)      WE14.
E)       WA02.
.

Thursday, March 3, 2011

Question no 991 : Value String WE01

In SAP MM, The Value String WE01 is used for which of the following scenario ?

(only one answer)

A)     Goods Receipt with reference to Purchase Order of Consignment Scenario.
B)     Goods Receipt with reference to Purchase Order with Stock Scenario.
C)     Goods Issue with reference to Purchase Order with Stock Scenario.
D)     Goods Receipt without reference for material free of charge.
E)     Goods Receipt with reference to Purchase Order with Consumable Scenario.
.

Question no 990 : Account Determination Setup

In SAP MM Account Determination, which of the following statements are TRUE ?

(more then one answers)

A)     Valuation Grouping Code can be activated or de-activated.
B)      Valuation Level can be activated or de-activated.
C)      Multiple material type can be assigned to one Account Category Reference.
D)      Multiple Account Category Reference can be assigned to one Valuation Class.
E)      New Value Strings can be customized.

Wednesday, March 2, 2011

Question no 989 : Value String

In SAP MM Account Determination, what are the standard influencing factors together with the movement type to derive the Value String for a particular Automatic Account Scenario ?

(more then one answers)

A)    Quantity Update indicator.
B)     Value Update indicator.
C)     Movement indicator.
D)     Special Stock indicator.
E)      Modifier.
.

Question no 988 : Partner Schemas

In SAP MM, Partners Schemas can be assigned to which of the following ?

(more then one answers)

A)    Purchasing Document types.
B)    Rebate Arrangement types.
C)    Vendor Account group.
D)    Material type.
E)     Material Document types.
.

Question no 987 : Client dependent data

Which of the following configurations are Client Independent (Cross Client) ?

(more then one answers)  

A)    Unit of Measure.
B)    Calender.
C)    Define Valuation level. 
D)    Enter Exchange rates.
E)    Set decimal places for currencies.
.

Question no 986 : Configuring Material Master

In SAP Material Master, which of the following is not an influencing factor in configuring the influencing factor for the screen sequence control ?

(only one answer)

A)    Transaction code.
B)    User.
C)    Material type.
D)    Plant.
E)     Industrial section.
.

Tuesday, March 1, 2011

Question no 985 : Standard Purchasing Organization

In SAP MM, the Standard Purchasing Organization is designed to be used for which of the following scenarios ?

(more then one answers)

A)     Consignment.
B)      Pipeline.
C)      Subcontracting.
D)      Third-Party.
E)      Returnable Transport Packaging.
.

Question no 984 : Fields Selection for Material Master fields

In SAP MM, which of the following are valid influencing factors using field reference for material master data fields ?

(more then one answers)

A)    Material Type.
B)     Procurement Type.
C)     User.
D)     Industrial Sector.
E)     Plant.
.

Question no 983 : Material Status parameters

In SAP MM, which of the following parameter control is possible via the material status ?

(more then one answers)

A)    Purchasing document creation.
B)     MRP run.
C)     Inventory Movement control.
D)     Invoice Verification control.
E)     Vendor Master creation.
.

Question no 982 : Material type configuration

In SAP MM, which of the following is configured within a material type ?

(more then one answers)

A)   Pipeline allowed.
B)   Costing via Quantity Structure.
C)   Quantity and Value updating.
D)   Item category group default.
E)    Order type default.
.