Which of the following statements are not true about Long Term Planning in SAP PP ?
(more then one answer)
A) Long Term Planning scenario can read non-active Planned Independent Requirements but
cannot read active Planned Independent Requirements.
B) A non-active version of the Planned Independent Requirement can only be used for
one Long Term Planning Scenario.
C) A particular Long Term Planning scenario can only read either active or non-active Planned
Independent Requirements but not both.
D) Planned Orders created by Long Term Planning run can be firmed and transferred to the
Operative Stocks Requirements List.
E) Firmed Planned Orders from the Operative Environment cannot be read into a Long Term Planning
Scenario.
.