This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes
▼
Tuesday, December 30, 2008
Monday, December 22, 2008
Tuesday, November 4, 2008
Wong on SAP Blogging
Welcome to my Blog,
Many of my students have asked me for SAP related mock examination questions. Here it is, I have created a blog for it. But don't ask me to send you a file for 100 questions or a list of the questions I have posted.
I am not sure if I will persist doing this but I have just learned how to Blog ! This I think is a good opportunity to share my experiences in SAP to both of past, present, future students and others who are interested in SAP.
I make mistakes occasionally but i will try to be as accurate as possible. I cannot guarantee the past can be equal to the present in SAP functionality as the company updates its software frequently. It is an information sharing blog only.
Enjoy SAP.
Cheers,
Wong Ching Wah
Nov 04, 2008
Many of my students have asked me for SAP related mock examination questions. Here it is, I have created a blog for it. But don't ask me to send you a file for 100 questions or a list of the questions I have posted.
I am not sure if I will persist doing this but I have just learned how to Blog ! This I think is a good opportunity to share my experiences in SAP to both of past, present, future students and others who are interested in SAP.
I make mistakes occasionally but i will try to be as accurate as possible. I cannot guarantee the past can be equal to the present in SAP functionality as the company updates its software frequently. It is an information sharing blog only.
Enjoy SAP.
Cheers,
Wong Ching Wah
Nov 04, 2008
Tuesday, September 30, 2008
Question no : 86 PP Master Data BOM Structuring
In SAP PP/LDM, Which of the following is NOT TRUE about the Bills of Material Structure ?
A) The BOM alternative identification can be an external number by the user.
B) A BOM can be assigned to multiple plants.
C) The BOM number is always an internal number range generated.
D) A bill of material first created will have an alternative of 1.
E) A BOM can be a maximum of 99 alternatives.
.
A) The BOM alternative identification can be an external number by the user.
B) A BOM can be assigned to multiple plants.
C) The BOM number is always an internal number range generated.
D) A bill of material first created will have an alternative of 1.
E) A BOM can be a maximum of 99 alternatives.
.
Friday, September 5, 2008
Question no :85 PP Master Data Configuration Profile for Super BOM
In SAP PP/LDM, Which of the following is NOT TRUE about Configuration Profile ?
A) A Constraint can be assigned to the Configuration Profile.
B) More then one class can be assigned to the Configuraiton Profile.
C) You assign class type 300 to the Configuration Profile.
D) A Procedure can be assigned to the Configuration Profile.
E) You assign the Bills of Material and Task list within he Configuration Profile
.
A) A Constraint can be assigned to the Configuration Profile.
B) More then one class can be assigned to the Configuraiton Profile.
C) You assign class type 300 to the Configuration Profile.
D) A Procedure can be assigned to the Configuration Profile.
E) You assign the Bills of Material and Task list within he Configuration Profile
.
Wednesday, September 3, 2008
Question no : 84 PM Execution Notification Creation possibilities
In SAP PM, Which of the following methods of maintenance notification creation is possible ?
I) Generate from the maintenance plan.
II) At the point of maintenance order confirmation.
III) Generate during maintenance order creation.
IV) Generate from the purchase requisition.
A) II, III
B) II, IV
C) I, II, IV
D) I, II, III
E) I, II, III, IV
.
.
I) Generate from the maintenance plan.
II) At the point of maintenance order confirmation.
III) Generate during maintenance order creation.
IV) Generate from the purchase requisition.
A) II, III
B) II, IV
C) I, II, IV
D) I, II, III
E) I, II, III, IV
.
.
Thursday, August 14, 2008
Friday, August 8, 2008
Question no : 83 PM Execution Notification features
In SAP PM, Which of the following functions allow you to obtain a swift overview of the condition and history of the object concerned within a maintenance notification ?
A) Link list.
B) Notification display.
C) Object information.
D) Action log.
E) History list
.
A) Link list.
B) Notification display.
C) Object information.
D) Action log.
E) History list
.
Wednesday, August 6, 2008
Question no : 82 PM Execution Notification creation
In SAP PM, A maintenance notification can be created ..
I) for a functional location.
II) for an equipment.
III) for a material with a serial number.
IV) for a functinal location and equipmnt
V) without an object.
A) I, II, III
B) I, II, IV
C) I, II, III, IV
D) II, IV
E) I, II, III, IV, V
.
I) for a functional location.
II) for an equipment.
III) for a material with a serial number.
IV) for a functinal location and equipmnt
V) without an object.
A) I, II, III
B) I, II, IV
C) I, II, III, IV
D) II, IV
E) I, II, III, IV, V
.
Monday, August 4, 2008
Question no : 81 PS Logistics Scheduling Logic influences
In SAP PS, Which of the following can have an influence on the scheduling logic of networks ?
I) Relationship to other networks.
II) The control key for the activity.
III) Dates of assigned WBS elements.
IV) The work center in the activities assigned.
A) I, II, III
B) I, II, IV
C) II, III, IV
D) II, III
E) I, II, III, IV
.
I) Relationship to other networks.
II) The control key for the activity.
III) Dates of assigned WBS elements.
IV) The work center in the activities assigned.
A) I, II, III
B) I, II, IV
C) II, III, IV
D) II, III
E) I, II, III, IV
.
Saturday, August 2, 2008
Question no : 80 CO Product Costing estimate
In SAP CO, The dates proposed from costing variant during the Material Cost Estimate is used in which of the following:
A) Stamped the validity period of the Cost Estimate (costing dates from/to)
B) Basis for determination of the Quantity Structure
C) Basis for the valuation date for the Materials
D) Basis for the valuation ate fro the Activities.
E) Basis for determination of the overhead keys for the Costing Sheet.
.
A) Stamped the validity period of the Cost Estimate (costing dates from/to)
B) Basis for determination of the Quantity Structure
C) Basis for the valuation date for the Materials
D) Basis for the valuation ate fro the Activities.
E) Basis for determination of the overhead keys for the Costing Sheet.
.
Wednesday, July 30, 2008
Question no : 79 LE WMS-PP Integration
In SAP WMS, In order to use the interface between Warehouse Management and Production Control You must create at least which of the following ?
A) at least one production supply area.
B) at least one control cycle.
C) at least one picking area.
D) at least one production supply area and one control cycle.
E) at least one production supply area, one control cycle, and one picking area.
.
A) at least one production supply area.
B) at least one control cycle.
C) at least one picking area.
D) at least one production supply area and one control cycle.
E) at least one production supply area, one control cycle, and one picking area.
.
Tuesday, July 29, 2008
Question no : 78 QM Master Data Inspection Characteristic in Inspection Plan
Which of the following Keys you can used to ensure the entry of Inspection Characteristics in mandatory in the Task list in general ?
A) Control Key.
B) System Status.
C) Standard Value Key.
D) Field Selection.
E) Operation Status.
.
A) Control Key.
B) System Status.
C) Standard Value Key.
D) Field Selection.
E) Operation Status.
.
Monday, July 28, 2008
Question no : 77 LDM Classification and OD
In SAP LDM, Which of the following Object Dependencies assignment is not allowed in Classifications ?
A) Assignment of Selection Condition to the Characteristics.
B) Assignment of Constrain to the Characteristics.
C) Assignment of Pre-condition to the Characteristics.
D) Assignment of Action to the Characteristics.
E) Assignment of Procedure to the Characteristics.
.
A) Assignment of Selection Condition to the Characteristics.
B) Assignment of Constrain to the Characteristics.
C) Assignment of Pre-condition to the Characteristics.
D) Assignment of Action to the Characteristics.
E) Assignment of Procedure to the Characteristics.
.
Sunday, July 27, 2008
SAP What is # 2 - What is Rounding Profile ?
You can find the "Rouding profile" parameter by navigating in the Customizing as follows:
Use IMG path -> PP -> MRP -> Planning -> Lot-Size Calculation -> Maintain Rounding Profile.
The Rounding Profile key contains a series of Rounding Values based on Thresh-hold values.
For example: lot size from 1 - 59 will be rounded to 20.
For example: lot size from 60 - 899 will then be rounded to 100.
as depicted below.
You can then assign the Rounding Profile to the MRP 1 view as below.
This is how it is calculated: (look at the S/R list below)
You can see there are 2 reservations : 588 and 660 one after another.
As the stock is 0, the system will first consider the lot size for 588.
Since lot size key is "EX", the gross lot size will be 588.
The gross lot size falls into thresh-hold value of 60 - 899 range.
with Rounding value of 100.
Therefore 588 will be rounded to 600. (Round up)
This result in 12 remnant stock (see the stock requirement list).
Next, let us look at the treatment for the second reservation of 660.
considering the remnant stock of 12.
Since lot size key is "EX", the gross lot size will be 648. .
The gross lot size falls into thresh-hold value of 60 - 899 range
with Rounding value of 100.
Therefore 648 will be rounded to 600. (Round down)
There is a 48 remaining demand to be treated.
And that falls into thresh-hold value of 1 - 59 range
with Rounding value of 20.
Therefore 48 will be rounded to 60. (Round up).
This will end with (600+60 = 660) for the second lot size.
CONCLUSION: The Rounding Profile feature results in the MRP system using the mechanics illustrated above to derive the final lot size for the supply MRP element.
APPLICATION: Especially useful when the supplier or the buyer is having different packing sizes instead of 1. For example, the supplier have sizes of 20 per pack as well as 600 per pack.
So, it may supply with 1 box of 600 pack-size and 2 box of 20 pack-size for the order size of 640.
CAUTION: It overrides the simple Rounding value in the MRP view. When you combine the Rounding Profile with different lot size key, check and simulate the results before using the combination.
.
Use IMG path -> PP -> MRP -> Planning -> Lot-Size Calculation -> Maintain Rounding Profile.
The Rounding Profile key contains a series of Rounding Values based on Thresh-hold values.
For example: lot size from 1 - 59 will be rounded to 20.
For example: lot size from 60 - 899 will then be rounded to 100.
as depicted below.
From SAP的学习和考试 Learning & Examination |
You can then assign the Rounding Profile to the MRP 1 view as below.
From SAP的学习和考试 Learning & Examination |
This is how it is calculated: (look at the S/R list below)
You can see there are 2 reservations : 588 and 660 one after another.
As the stock is 0, the system will first consider the lot size for 588.
Since lot size key is "EX", the gross lot size will be 588.
The gross lot size falls into thresh-hold value of 60 - 899 range.
with Rounding value of 100.
Therefore 588 will be rounded to 600. (Round up)
This result in 12 remnant stock (see the stock requirement list).
Next, let us look at the treatment for the second reservation of 660.
considering the remnant stock of 12.
Since lot size key is "EX", the gross lot size will be 648. .
The gross lot size falls into thresh-hold value of 60 - 899 range
with Rounding value of 100.
Therefore 648 will be rounded to 600. (Round down)
There is a 48 remaining demand to be treated.
And that falls into thresh-hold value of 1 - 59 range
with Rounding value of 20.
Therefore 48 will be rounded to 60. (Round up).
This will end with (600+60 = 660) for the second lot size.
From SAP的学习和考试 Learning & Examination |
APPLICATION: Especially useful when the supplier or the buyer is having different packing sizes instead of 1. For example, the supplier have sizes of 20 per pack as well as 600 per pack.
So, it may supply with 1 box of 600 pack-size and 2 box of 20 pack-size for the order size of 640.
CAUTION: It overrides the simple Rounding value in the MRP view. When you combine the Rounding Profile with different lot size key, check and simulate the results before using the combination.
.
Saturday, July 26, 2008
PP Planning Strategy 52
Strategy '50' is used for MTO scenario where
PIR is allowed but Production for the FG is only allowed
when Sales Order comes in. The reason for
Strategy '50' over '20' is Sales Order lead time may be
too short for component planning. Hence, a PIR is
allowed with Strategy '50' to plan for the components.
Strategy '52' is a derivation of '50' and it is designed
for the MTS scenario. Here, the Production for the FG
is only allowed when the Sales Order comes in
(similar to '50' using the Order type 'VP' and Conversion Indicator).
However, the PIR will proceed with the Component Planning.
You can use the Individual/Collective Indicator
for both '52' and '50' to control the behavior of
the components to follow its parent or not.
Thursday, July 17, 2008
Question no : 76 PM Master Data Structural Indicator
In SAP PM/CS, Which of the following is True about the use of "Structure Indicator" ?
A) It is used in both the Functional Location and Equipment creation process.
B) It is assigned to the Equipment category.
C) The number range Group is used to contain the valid internal and external number ranges.
D) It can only use internal number ranges generated by SAP.
E) The maximum level is 40.
.
A) It is used in both the Functional Location and Equipment creation process.
B) It is assigned to the Equipment category.
C) The number range Group is used to contain the valid internal and external number ranges.
D) It can only use internal number ranges generated by SAP.
E) The maximum level is 40.
.
Wednesday, July 16, 2008
Question no : 75 PP MRP basics activation
The following are standard mandatory fields in the MRP views (when a material is activated for MRP run) in the standard MRP system except?
A) MRP type.
B) MRP controller.
C) Lot size key.
D) Procurement type.
E) Goods receipt processing time.
.
A) MRP type.
B) MRP controller.
C) Lot size key.
D) Procurement type.
E) Goods receipt processing time.
.
Tuesday, July 15, 2008
Question no : 74 MM Purchasing RFQ/Quotation concept
Which of the following statement is Not True about RFQ and Quotation ?
A) Collective Number is in the Header of the RFQ.
B) RFQ and Quotation document type uses the same number ranges.
C) An RFQ can be created with an Account Assignment.
D) A One time vendor can be used to create an RFQ.
E) A rejection letter can be printed from a rejected Quotation.
.
A) Collective Number is in the Header of the RFQ.
B) RFQ and Quotation document type uses the same number ranges.
C) An RFQ can be created with an Account Assignment.
D) A One time vendor can be used to create an RFQ.
E) A rejection letter can be printed from a rejected Quotation.
.
Monday, July 14, 2008
Question no : 73 MM Account Determination Account Assignment Category
Which of the following key is used to different influence G/L Account Determination via the Account Assignment Category ?
A) Cost object.
B) Account grouping code.
C) Account key.
D) Account category reference.
E) Valuation grouping code.
.
A) Cost object.
B) Account grouping code.
C) Account key.
D) Account category reference.
E) Valuation grouping code.
.
Sunday, July 13, 2008
Question no : 72 MM Account Determination Principles
Which of the following are TRUE regarding features in Automatic Account Determination ?
I) Valuation grouping code is mandatory.
II) You can assign more then one plant to a Valuation grouping code.
III) You can assign more than one valuation class to a Valuation grouping code.
IV) You can assign one or multiple material type to an Account category reference.
V) You can assing one or multiple valuation class to an Account category reference.
A) I, II, V
B) I, III, IV, V
C) II, III, IV
D) II, IV, V
E) II, III, IV, V
.
I) Valuation grouping code is mandatory.
II) You can assign more then one plant to a Valuation grouping code.
III) You can assign more than one valuation class to a Valuation grouping code.
IV) You can assign one or multiple material type to an Account category reference.
V) You can assing one or multiple valuation class to an Account category reference.
A) I, II, V
B) I, III, IV, V
C) II, III, IV
D) II, IV, V
E) II, III, IV, V
.
Thursday, July 3, 2008
Question no : 71 PP MRP Opening Date
The duration between the "Opening date" and the "Order start date" for a planned order is called the "Opening Period", in which parameter the key is configured in the MRP view in the material master ?
A) Safety time profile.
B) Scheduling margin key.
C) Lot sizing key.
D) MRP controller.
E) Strategy group.
.
A) Safety time profile.
B) Scheduling margin key.
C) Lot sizing key.
D) MRP controller.
E) Strategy group.
.
Question no : 70 PP MRP "NEUPL"
Which of the following planning run transactions can be used for "NEUPL" ?
I) Single-Item-Single-Level MRP run.
II) Single-Item-Multi-Level MRP run.
III) On-line MPR run at the Plant level.
IV) Background MRP run at the Plant level.
V) Interactive MRP run.
A) I, II, III
B) III, IV
C) IV
D) V
E) I, II, III, IV, V
I) Single-Item-Single-Level MRP run.
II) Single-Item-Multi-Level MRP run.
III) On-line MPR run at the Plant level.
IV) Background MRP run at the Plant level.
V) Interactive MRP run.
A) I, II, III
B) III, IV
C) IV
D) V
E) I, II, III, IV, V
Wednesday, July 2, 2008
Question no : 69 PP MRP Floats
"Float before production" and "Float after production" time buffers are to be set using which time Parameter ?
A) Scheduling Margin Key.
B) Routing Operation Detail.
C) Production Scheduler Profile.
D) Production Scheduler.
E) MRP Controller.
.
A) Scheduling Margin Key.
B) Routing Operation Detail.
C) Production Scheduler Profile.
D) Production Scheduler.
E) MRP Controller.
.