This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes
▼
Thursday, January 31, 2008
Question on : 6 PP Master Data Material BOM
Which of the following objects you CANNOT assign to a "Material BOM" ?
I) Material Master.
II) Service Master.
III) Document from the DMS module.
IV) Class.
V) Production Resource Tool.
A) II, III, IV, V
B) II, III, IV.
C) II, IV, V.
D) II, III, IV, V.
E) II, V.
.
I) Material Master.
II) Service Master.
III) Document from the DMS module.
IV) Class.
V) Production Resource Tool.
A) II, III, IV, V
B) II, III, IV.
C) II, IV, V.
D) II, III, IV, V.
E) II, V.
.
Wednesday, January 30, 2008
Tuesday, January 29, 2008
Question no : 5 PP MRP Material Master MRP View
What is TRUE regarding "you cannot access the stock requirements list of a material master if ...."
I) You did not create at least MRP 1 & 2 views of the material master.
II) You did create the MRP view but you forgot to enter a valid MRP type in the MRP 1 view.
III) The material does not have any existing demand and supplies.
IV) You left out the Purchasing view for that material master.
V) Only the Basic view currently is created for that material master.
A) V only.
B) II, V.
C) IV, V.
D) II, IV, V.
E) I, II, III, IV, V.
.
I) You did not create at least MRP 1 & 2 views of the material master.
II) You did create the MRP view but you forgot to enter a valid MRP type in the MRP 1 view.
III) The material does not have any existing demand and supplies.
IV) You left out the Purchasing view for that material master.
V) Only the Basic view currently is created for that material master.
A) V only.
B) II, V.
C) IV, V.
D) II, IV, V.
E) I, II, III, IV, V.
.
Monday, January 28, 2008
Question no : 4 PP MRP Logic
When will the system flag the "NETCH" indicator for a material master with strategy group 40 ?
(demands = planned independent requirements)
I) New demands are introduced within the planning horizon.
II) New demands are introduced outside the planning horizon.
III) The lot size key in the MRP 1 view is changed.
IV) The material status in the MRP 1 view is selected for MRP activation.
V) Previous demands are removed from the planning horizon.
A) I, II, V
B) I, V
C) II, V
D) I, II, III, IV, V
E) I, II, III, V
.
(demands = planned independent requirements)
I) New demands are introduced within the planning horizon.
II) New demands are introduced outside the planning horizon.
III) The lot size key in the MRP 1 view is changed.
IV) The material status in the MRP 1 view is selected for MRP activation.
V) Previous demands are removed from the planning horizon.
A) I, II, V
B) I, V
C) II, V
D) I, II, III, IV, V
E) I, II, III, V
.
Sunday, January 27, 2008
Question no : 3 PP MRP Lot Sizing Rule
Determine the expected lot size calculated by MRP based on the following data:
Current stock is 100 units
MRP type is Re-order point
Re-order quantity is 500
Fixed Lot size is 300
Satety stock is 200
Rounding value is 50
A) 1 planned order of 400 units.
B) 1 planned order of 600 units.
C) 2 planned orders of 300 units each.
D) 3 planned orders of 200 units each.
E) 1 planned order of 200 units and another planned order of 300 units.
.
Current stock is 100 units
MRP type is Re-order point
Re-order quantity is 500
Fixed Lot size is 300
Satety stock is 200
Rounding value is 50
A) 1 planned order of 400 units.
B) 1 planned order of 600 units.
C) 2 planned orders of 300 units each.
D) 3 planned orders of 200 units each.
E) 1 planned order of 200 units and another planned order of 300 units.
.
Wednesday, January 23, 2008
Sunday, January 20, 2008
Question no: 2 MM Master Data Material Master Status
The material status in the MRP 1 view can be used to do the following except:
A) block a material from being created with a Routing.
B) block a material from being assigned as a BOM item.
C) block a material from being inserted in a purchased order.
D) block a material from goods issue but allow goods receipt.
E) block a material from being executed in a cost estimate run.
.
A) block a material from being created with a Routing.
B) block a material from being assigned as a BOM item.
C) block a material from being inserted in a purchased order.
D) block a material from goods issue but allow goods receipt.
E) block a material from being executed in a cost estimate run.
.
Wednesday, January 16, 2008
Monday, January 14, 2008
Question no: 1 MM Master Data Material Group
The Material Group in the Material Master can be used for which of the following features in SAP ?
I) Material Group Info Record.
II) Material Group Contract via a special item category in the Contract.
III) Material Group Scheduling Agreement via a special item category in the Contract.
IV) Material Group Pricing Conditions.
Select the best answer from the following:
A) I only.
B) I, II only.
C) I, II, III only.
D) I, II, IV only.
E) I, II, III, IV.
.
I) Material Group Info Record.
II) Material Group Contract via a special item category in the Contract.
III) Material Group Scheduling Agreement via a special item category in the Contract.
IV) Material Group Pricing Conditions.
Select the best answer from the following:
A) I only.
B) I, II only.
C) I, II, III only.
D) I, II, IV only.
E) I, II, III, IV.
.